Facilities Project
Performing Arts Center Renderings

Rendering of a new Performing Arts Center at Canal Winchester High School, showing a modern brick entrance with large windows, signage, landscaped seating areas, and a main entrance for students and visitors.

Rendering of a new Performing Arts Center at Canal Winchester High School, showing a modern brick entrance with large windows, signage, landscaped seating areas, and a main entrance for students and visitors.

Rendering of a new Performing Arts Center at Canal Winchester High School, showing a modern brick entrance with large windows, signage, landscaped seating areas, and a main entrance for students and visitors.
Baseball and Softball Complex Renderings

Aerial rendering of a new baseball and softball complex with one baseball field and two softball fields, all with turf infields, dugouts, fencing, a central press box, and nearby parking.

Aerial rendering of a new baseball and softball complex with one baseball field and two softball fields, all with turf infields, dugouts, fencing, a central press box, and nearby parking.
Field House Rendering

Rendering of a new field house building at Canal Winchester High School near the stadium, with a large indoor turf space, exterior sidewalks, and surrounding athletic fields and track visible in the background.
Timeline
Bleachers (Estimated 4-month duration)
- Start: March 16, 2026
- Finish: July 31, 2026
Ballfields (Estimated 5-month duration)
- Start: June 1, 2026
- Finish: November 30, 2026
Athletic Fieldhouse (Estimated 12-month duration)
- Start: May 1, 2026
- Finish: May 31, 2027
Performing Arts Center (Estimated 14-month duration)
- Start: May 1, 2026
- Finish: September 10, 2027
Fuel Station Relocation (Estimated 3-month duration)
- Start: April 13, 2026
- Finish: July 5, 2026