As we settle into fall, the Facilities Improvement Project continues to make steady headway!

The new ballfields continue to advance, with the outline of the fields beginning to take shape. Storm utilities are complete, allowing crews to move forward with drainage work for the baseball practice field and begin setting foundations. Up next, crews will install the curb and parking lot pad, along with water and electrical services.

At the Performing Arts Center, crews have completed foundations, foundation block, restroom plumbing, and the auditorium slope cut. Northeast underground plumbing and electrical work, along with orchestra pit waterproofing, are also progressing on schedule. Up next is Phase 1 of the slab-on-grade work.

At the fieldhouse, crews are preparing sanitary systems before foundation work can begin. Once these systems are in place, crews will begin underground plumbing, electrical, and water services, along with foundation and storm drainage work.

Construction vehicles and workers are scattered across a large, dirt-filled lot in the foreground, with a residential area and industrial buildings visible in the background.

September 2026: The Facilities Improvement Project continues to make steady progress, with work advancing at the new ballfields, Performing Arts Center, and fieldhouse. Crews are moving into the next phases of construction, including foundations, utilities, drainage, parking areas, and concrete work across the three project sites.

Construction workers build a curved concrete block wall in a dirt pit, with a larger building structure and heavy machinery under a cloudy sky in the background.

September 2026: The Facilities Improvement Project continues to make steady progress, with work advancing at the new ballfields, Performing Arts Center, and fieldhouse. Crews are moving into the next phases of construction, including foundations, utilities, drainage, parking areas, and concrete work across the three project sites.

Concrete block foundations sit on a gravel lot in the foreground, with construction equipment and a sunset sky in the background.

September 2026: The Facilities Improvement Project continues to make steady progress, with work advancing at the new ballfields, Performing Arts Center, and fieldhouse. Crews are moving into the next phases of construction, including foundations, utilities, drainage, parking areas, and concrete work across the three project sites.

A construction site with dirt piles and heavy machinery sits in the foreground next to a school building and athletic field, with a residential neighborhood and lush greenery in the background.

September 2026: The Facilities Improvement Project continues to make steady progress, with work advancing at the new ballfields, Performing Arts Center, and fieldhouse. Crews are moving into the next phases of construction, including foundations, utilities, drainage, parking areas, and concrete work across the three project sites.

A construction site with piles of gravel, steel beams, and a large dirt pit sits in the foreground, while a sports stadium and track are visible in the background.

September 2026: The Facilities Improvement Project continues to make steady progress, with work advancing at the new ballfields, Performing Arts Center, and fieldhouse. Crews are moving into the next phases of construction, including foundations, utilities, drainage, parking areas, and concrete work across the three project sites.

A construction site and buildings occupy the foreground, while a football field surrounded by a running track sits in the background.

September 2026: The Facilities Improvement Project continues to make steady progress, with work advancing at the new ballfields, Performing Arts Center, and fieldhouse. Crews are moving into the next phases of construction, including foundations, utilities, drainage, parking areas, and concrete work across the three project sites.

Construction equipment and piles of dirt occupy a large sandy lot in the foreground, with a residential neighborhood and green trees in the background.

September 2026: The Facilities Improvement Project continues to make steady progress, with work advancing at the new ballfields, Performing Arts Center, and fieldhouse. Crews are moving into the next phases of construction, including foundations, utilities, drainage, parking areas, and concrete work across the three project sites.

A large, sandy construction site with heavy machinery and a sediment pond occupies the foreground, while a residential neighborhood with houses and green lawns lines the background.

September 2026: The Facilities Improvement Project continues to make steady progress, with work advancing at the new ballfields, Performing Arts Center, and fieldhouse. Crews are moving into the next phases of construction, including foundations, utilities, drainage, parking areas, and concrete work across the three project sites.

A construction site with dirt, machinery, and pipes occupies the foreground, while a residential neighborhood with houses and trees fills the background.

September 2026: The Facilities Improvement Project continues to make steady progress, with work advancing at the new ballfields, Performing Arts Center, and fieldhouse. Crews are moving into the next phases of construction, including foundations, utilities, drainage, parking areas, and concrete work across the three project sites.

Construction equipment and pipes sit on a large dirt lot in the foreground, with a residential neighborhood and a commercial building in the background.

September 2026: The Facilities Improvement Project continues to make steady progress, with work advancing at the new ballfields, Performing Arts Center, and fieldhouse. Crews are moving into the next phases of construction, including foundations, utilities, drainage, parking areas, and concrete work across the three project sites.

A blue boom lift stands within the concrete foundations of a building under construction, with completed brick structures and a dirt lot in the background.

September 2026: The Facilities Improvement Project continues to make steady progress, with work advancing at the new ballfields, Performing Arts Center, and fieldhouse. Crews are moving into the next phases of construction, including foundations, utilities, drainage, parking areas, and concrete work across the three project sites.

A V-shaped concrete foundation is laid out on a dirt construction site, with a residential neighborhood and green lawns in the background.

September 2026: The Facilities Improvement Project continues to make steady progress, with work advancing at the new ballfields, Performing Arts Center, and fieldhouse. Crews are moving into the next phases of construction, including foundations, utilities, drainage, parking areas, and concrete work across the three project sites.

A muddy construction site filled with vehicles and equipment sits in the foreground, with a residential neighborhood and lush green trees in the background.

September 2026: The Facilities Improvement Project continues to make steady progress, with work advancing at the new ballfields, Performing Arts Center, and fieldhouse. Crews are moving into the next phases of construction, including foundations, utilities, drainage, parking areas, and concrete work across the three project sites.

A blue boom lift extends over a curved concrete wall in the foreground of a construction site, with grey block walls and scaffolding in the background.

September 2026: The Facilities Improvement Project continues to make steady progress, with work advancing at the new ballfields, Performing Arts Center, and fieldhouse. Crews are moving into the next phases of construction, including foundations, utilities, drainage, parking areas, and concrete work across the three project sites.

A construction site with concrete foundations and machinery sits in the foreground, bordered by red brick buildings and a parking lot in the background.

September 2026: The Facilities Improvement Project continues to make steady progress, with work advancing at the new ballfields, Performing Arts Center, and fieldhouse. Crews are moving into the next phases of construction, including foundations, utilities, drainage, parking areas, and concrete work across the three project sites.