July 2026 Facilities Project Update

Silver bleachers with ramps and stairs are in the foreground, with a black track and trees under a cloudy sky in the background.
Megan Anthony

Exciting progress continues for the Facilities Project! Construction continues across the district, with bleacher work nearing completion and site preparation advancing for the baseball and softball complex, Performing Arts Center, and fieldhouse.

The home and visitor bleacher additions are complete, and structural inspections are finalized. Fencing installation is the last step to complete the bleacher project!

At the baseball and softball complex, the existing scoreboard has been removed, and both field demolition and tree removal and protection are now complete. Crews have begun working on the detention pond and will soon move into constructing the parking lot pad, installing foundations, and completing underground utilities to prepare the site for the next phase.

Preparation for the new Performing Arts Center is ramping up. Asphalt removal, gas line relocation, and utility surveying have all been completed. Crews are beginning work for the building pad and preparing for domestic and fire water line installation, domestic hot and cold-water valve installation, fiber optic relocations, and MEP (mechanical, electrical, plumbing) rough-ins. Foundation work and storm system installation are also on the horizon.

At the future fieldhouse, tree removal and protection have been completed, while asphalt and sidewalk demolition continue. Next will be grading/earthwork and underground utilities, preparing the site for vertical construction.

Empty bleachers and a paved walkway are in the foreground, while a scoreboard and buildings are visible in the background under a cloudy sky.

July 2026: Construction continues across the district, with bleacher work nearing completion and site preparation advancing for the baseball and softball complex, Performing Arts Center, and fieldhouse.

Silver bleachers with ramps and stairs are in the foreground, with a black track and trees under a cloudy sky in the background.

July 2026: Construction continues across the district, with bleacher work nearing completion and site preparation advancing for the baseball and softball complex, Performing Arts Center, and fieldhouse.

A concrete path leads through dry grass towards a stadium with bleachers, while a track and field are visible in the background under a cloudy sky.

July 2026: Construction continues across the district, with bleacher work nearing completion and site preparation advancing for the baseball and softball complex, Performing Arts Center, and fieldhouse.

A freshly mowed grassy slope in the foreground leads to a stadium and trees in the background under a cloudy sky.

July 2026: Construction continues across the district, with bleacher work nearing completion and site preparation advancing for the baseball and softball complex, Performing Arts Center, and fieldhouse.

Tire tracks mark the dry, grassy foreground of a construction site where excavators work amidst trees and houses in the background under a cloudy sky.

July 2026: Construction continues across the district, with bleacher work nearing completion and site preparation advancing for the baseball and softball complex, Performing Arts Center, and fieldhouse.

Muddy, disturbed earth in the foreground leads to a shallow pond and a line of trees with houses beyond under a cloudy sky.

July 2026: Construction continues across the district, with bleacher work nearing completion and site preparation advancing for the baseball and softball complex, Performing Arts Center, and fieldhouse.

Dry, patchy grass fills the foreground of a construction site where bulldozers work on a dirt mound, with a suburban neighborhood visible in the background under a cloudy sky.

July 2026: Construction continues across the district, with bleacher work nearing completion and site preparation advancing for the baseball and softball complex, Performing Arts Center, and fieldhouse.

Piles of dirt and gravel in the foreground surround a construction site with a large brick building and an excavator in the background under a cloudy sky.

July 2026: Construction continues across the district, with bleacher work nearing completion and site preparation advancing for the baseball and softball complex, Performing Arts Center, and fieldhouse.

A cracked concrete path leads through a grassy area with a small shed and a fenced field in the background under a clear blue sky.

July 2026: Construction continues across the district, with bleacher work nearing completion and site preparation advancing for the baseball and softball complex, Performing Arts Center, and fieldhouse.